How to build a better small biogas unit
Putting in the waste
VIEW THE DOCUMENTTime
Temperature
VIEW THE DOCUMENTScum
VIEW THE DOCUMENTWhen the gas is made
VIEW THE DOCUMENTTaking care of your biogas unit
VIEW THE DOCUMENTMaking more biogas
What more can you do?

Time

104. It may take up to three weeks or even a month for the waste in your new biogas unit to begin making gas. After that, the unit will continue to make gas for about eight weeks.

105. During these eight weeks half of the gas will be made in the first two or three weeks and the rest in the last five or six weeks.

106. If you find that too little gas is being made in the last weeks empty the unit and start again.